Road Resurfacing & Construction Updates

Maillet Sommes Morgan Stormwater Wetlands

 UPDATE

May 18, 2023

Project has officially kicked off with the contractor expected to fully mobilize over the next few weeks. Please see our website at readingma.gov/msm for more information and use caution if in the area


Washington Street Resurfacing

(Main St. to Village St.)

UPDATE

May 18, 2023

Washington Street line painting is expected over the next week

 

Lowell Street Resurfacing

(Salem Street to #255 Lowell Street)

UPDATE

May 18, 2023

Line Painting of Lowell Street is expected to take place Friday May 26th. The road will be closed and detours will be in place. Access to driveways will be limited depending on the work area for a short period of time. Please do not drive on wet paint within the work zone. 


Auburn Street Water Tank:

UPDATE

May 18, 2023

The pedestal pour is ongoing with work to be completed over the next month. The tank installation should be complete by the end of summer or early fall.

 

Downtown Water Main Improvements: 

UPDATE

May 18, 2023

 Contractor has completed all punch list items as of tomorrow April 14th. Sometime this summer final trench paving will be completed. 

 

Sturges Park Pump Station:

UPDATE

May 18, 2023

The new pump station is installed, we are working on final instrumentation connections, work should be completed this spring.  

 

* UPCOMING PROJECTS *

Walkers Brook Drive Water Main Improvements (Spring 2023)

Gazebo Drive Pump Station (Summer 2023)

Downtown Drain Lining (Summer 2023)

2023 Road Resurfacing Program